Here’s the current dive plan: Go to the sea floor, deploy and connect instruments, collect some data, return to ship. Sounds straightforward, but this is a scheduled 32-hour dive and the devil is in the details and the unexpected events. Routine as it can sometimes seem to me watching the unflappable ROPOS operators, meticulous engineers and calm scientists in the ROPOS control room, the team is dealing with continually changing conditions, equipment issues, opportunities, and problems.
For one thing, the weather picked up yesterday and the ship started rocking and rolling, so they cut the last dive short and put off an instrument survey for the next dive. The team wanted to get ROPOS up quickly so they could turn around and dive again with a basket full of instruments that will help complete the subnet at Axial seamount.
With waves increasing to about 2 meters (6 feet) the launch crane operator waited for a swell to pass and eased ROPOS into the water and on its way down before the next surge pulled down on the wire holding the ROV. Ninety minutes later, ROPOS was on the bottom, setting down the instrument basket and getting to work. Even removing instruments from the basket is a well-choreographed series of events, I’ve heard it described here as a ballet. It’s a ballet with four principal dancers: an ROV driver, two men each operating a robotic arm, and the vehicle itself. This team is so skilled and their moves so well-rehearsed, they often don’t even speak to each other as one robotic arm clamps on the basket, the other lifts out an instrument and ROPOS floats up and across the sea floor to find the precise location to deploy the seismometer. Setting the instrument platform down on a flat patch of lava, a robotic arm turns four screws in succession to level the instrument (the difference between this piece of construction equipment and the bubble level familiar to carpenters is the deep sea levelers use a marble rather than a bubble to find the center point). Only when it’s settled and level will ROPOS connect the instrument to the cable, awaiting the flow of electrons from the ship to awaken the instruments.
On this dive, the team deployed two seismometers and one “tiltometer,” more properly known as the bottom pressure tilt meter. This instrument was developed by Bill Chadwick at NOAA’s Pacific Marine Environmental Laboratory to record the expansion and contraction of the volcano from the flow of magma below. Bill was a scientist-in-residence at the Exploratorium last year and he’s been studying the Axial volcano for two decades. He was on the ship in spirit and on the phone last night as the ROPOS team eased his instrument in place. It’s painstaking work and you can sometimes see the scientists and engineers squirm in their seats, wanting to reach out and help ROPOS complete this delicate task. But their instruments are in good hands, these Canadians know their ROV and they finished the task ahead of schedule.
Then it was time for the engineers to flip a switch (actually click on a computer screen) and activate the cable network that powers the instruments and carries data back through ROPOS to the ship. The plan was to collect data for six hours to make sure the instruments were working and the subnet infrastructure was ready to be plugged into the primary network that connects to the shore station and the Internet when the observatory goes live next year.
Once all the equipment was turned on and systems verified, the team in the ROPOS control room settled in to wait for data. For those awake at 4:30 AM, they didn’t have to wait long. Within 15 minutes, there was a tremor on Axial, picked up by one seismometer, then the other in quick succession. It was a nice moment for the night owls working on the R/V Thompson and for those of us who woke up to a beautiful data graph the next morning.

First in-situ earthquake recorded in real-time at Axial Volcano.